Delay to the Cycle 10 configuration schedule due to transporter issues

Published: 26 Oct 2023
A European ALMA antenna takes a ride on a transporter

The start of antenna relocations between configuration C-8 and C-7, originally scheduled for October 20th, will be delayed until at least November 10th.  Following recent inspections, it was found that both antenna transporters need urgent maintenance. ALMA has thus decided to take both transporters out of operation to proceed with the necessary repairs, to prevent a longer-term stoppage of antenna relocations. This situation will have an impact on the remaining Cycle 10 configuration calendar.  As far as possible, ALMA will take mitigation actions to ensure that the observing queue is populated. A further announcement will be posted on the Science Portal once the technical issues have been solved and the specific impact on the configuration schedule has been established. We regret any inconvenience or impact experienced by our ALMA users due to this issue. If you have any questions, or have comments or concerns, please contact your local ALMA Regional Centre via the ALMA Helpdesk at https://help.almascience.org/