Company or Institution |
Service |
Logo |
Start date |
Planned end date |
M1LCS Cabinets Heat Exchangers |
Nov 2020 |
Dec 2021 |
||
Design and construction of the Paranal ELT Technical Facility |
Mar 2018 |
Jul 2019 (completed) |
||
Dome and telescope structure design and construction contract |
May 2016 |
May 2023 |
||
M4 mirror phase 1 preliminary design |
May 2012 |
Jan 2015 (completed) |
||
M4 mirror unit final design and manufacturing |
Jun 2015 |
Jan 2023 |
||
Design and manufacturing of M1 mirror coating plants |
Jun 2018 |
Dec 2021 |
||
AS Scientific Products Ltd |
Liquid Nitrogen infrastructure |
Dec 2023 |
April 2027 |
|
M1 mirror segment supports design and qualification units |
Feb 2015 |
Oct 2017 (completed) |
||
Core integration infrastructure |
Jul 2017 |
Jun 2020 |
||
ISVV consultancy services |
Jan 2016 |
Dec 2021 |
||
Freight Forwarding Services |
Oct 2020 |
Jul 2025 |
||
Dataflow Software Components for the ELT |
Nov 2018 |
Dec 2028 |
||
FAMES (FOGALE, Micro-Epsilon) |
M1 mirror edge sensors design and manufacturing |
Jan 2017 |
May 2022 |
|
Design, manufacture, transport, on-site assembly and verification of the ELT M1 Washing and Stripping Plant |
Jan 2020 |
Jan 2024 |
||
C-RED cameras for the MORFEO instrument |
Jul 2018 |
Sep 2020 (completed) |
||
Road and platform construction |
Dec 2013 |
Feb 2017 (completed) |
||
PFS-A main system design and manufacturing |
Apr 2018 |
Feb 2024 |
||
Main responsible for the MORFEO instrument — full list of Consortium partners can be found here |
Feb 2016 |
Aug 2025 |
||
PA consultancy services |
Jan 2016 |
Dec 2021 |
||
Main responsible for the MICADO instrument — full list of Consortium partners can be found here |
Oct 2015 |
Mar 2025 |
||
Main responsible for the METIS instrument — full list of Consortium partners can be found here |
Oct 2015 |
Mar 2026 |
||
M1 mirror position actuators |
Jun 2017 |
Sep 2022 |
||
M1LCS Cabinets Procurement and AIV |
Dec 2020 |
Jul 2022 |
||
Consultancy support |
Jun 2013 |
May 2021 |
||
Electrical power supply 2017 — |
|
|
|
|
M4 mirror shells supply |
Jul 2015 |
Nov 2023 |
||
M2 mirror and auxiliary equipment supply |
Jul 2016 |
Feb 2024 |
||
M3 mirror and auxiliary equipment supply |
Feb 2017 |
Sep 2023 |
||
M1 mirrors polishing |
May 2017 |
Jun 2023 |
||
M5 mirror blank and polishing |
Mar 2019 |
Sep 2024 |
||
M2 mirror blank supply |
Jan 2017 |
Jan 2019 (completed) |
||
M3 mirror blank supply |
Jan 2017 |
Jul 2019 (completed) |
||
M1 mirror blanks supply |
May 2017 |
Sep 2022 |
||
Construction all risks insurance |
Mar 2018 |
Mar 2026 |
||
M2 and M3 mirror cell design and manufacturing |
Jan 2017 |
Jul 2022 |
||
Supply, and installation of ABC power substations (23kV + 0.4 kV) |
Oct 2016 |
Jul 2018 (completed) |
||
Main responsible for the HARMONI instrument — full list of Consortium partners can be found here |
Oct 2015 |
Apr 2026 |
||
Production of adaptive optics wavefront sensing cameras |
Dec 2022 |
Dec 2024 |
||
Infrared detectors for the HARMONI, MICADO, METIS instruments |
Jul 2018 |
Jan 2023 |
||
Laser Projection Subunits |
Dec 2020 |
Mar 2025 |
||
Laser sources |
Dec 2017 |
Dec 2022 |
||
M1 mirror segment supports design and qualification units |
Jan 2015 |
Jul 2017 (completed) |
||
M1 mirror segment supports series production |
Apr 2018 |
May 2022 |